johnjolly7551 replied to the topic Builders Miscalculate Material Quantities Causing Project Delays in the forum Forum example #1 2 weeks, 6 days ago
<p>Malik here, representing F&K Estimatings. One practical way to catch a shortage before ordering is to keep the measured quantity separate from the purchasing quantity.</p>
<p>For example, a plain 12 ft by 18 ft slab at 4 inches thick is 72 cubic feet, or about 2.67 cubic yards, before any allowance. Thickened edges, steps and openings need…[Read more]